Further delays hit key Scottish infrastructure

The Scottish Government has said it will no longer be able to deliver to schedule the projects in its key infrastructure pipeline, including the new HMP Glasgow super prison and the dualling of the A9.

Almost half of the schemes in its latest major capital projects update had been hit by further delays in the past year, it said, blaming high levels of inflation in the construction sector, lower-than-expected levels of capital grant and the need to redirect resources towards new infrastructure priorities.

Weather-sensitive work, unforeseen construction site difficulties, design reviews, longer commissioning periods, health and safety issues and the capacity of supply chains also contributed to delays.

“Progress is being made to deliver key infrastructure investments and major projects have been delivered against a continuing backdrop of challenging economic and financial conditions,” it said.

However, cost pressures meant it was no longer feasible to deliver the work to the original timeline.

“The high levels of construction inflation in recent years, combined with lower-than-expected capital grant and the need to prioritise funding to new additions to the infrastructure pipeline, has meant that the infrastructure pipeline we set out in the 2021 Infrastructure Investment Plan (IIP) cannot be delivered in full within the timeframe covered by the IIP,” it said.

It confirmed that the £1bn HMP Glasgow job, handed to Kier earlier this year, would be one of the projects to be delayed, with completion now due at the end of 2028.

Early works have been underway on the site since October, paving the way for a new facility with the capacity for 1,344 prisoners, replacing nearby HMP Barlinnie, Scotland’s largest prison.

But according to the update, the complex has been delayed for a year, with costs expected to rise by £252m.

The government blamed inflationary pressures within the construction industry, which it said had impacted on the costs of raw materials, labour and production globally.

It also said the current volume of public sector prison new-build works had put pressure on the capacity of the supply chain.

The long-awaited dualling of the A9 between Perth and Inverness will also be pushed back by around six months.

Balfour Beatty was named last year as the successful bidder for the 9.6km stretch between Tomatin and Moy.

The final tender price was £184.7m, with a total forecast project cost of £308m, which would remain unchanged, according to the update.

However, the project, initially expected to be up and running by the end of 2027, will now be operational at the end of spring 2028.

“This is later than previously reported and followed receipt and review of the contractor’s initial works programme, which required additional time for construction of the works than had been originally estimated,” it said.

It attributed the delay to factors including seasonal constraints on weather-sensitive work and environmental restrictions for working in watercourses.

Delays have also hit a new national treatment centre planned for NHS Forth Valley.

The new 30-bed ward in Larbert, to be delivered by Portakabin, would have allowed an additional 1,500 operations to be carried out each year.

Although the capital cost of the scheme remains unchanged at £11.1m, the delivery of the new ward has been hindered by a number of construction issues, including the incorrect installation of pipework and risks in relation to fire compliance measures, the report said.

No opening date for the ward, which was due to open last year, has yet been confirmed.

“All parties are working to develop a technical solution to resolve these issues,” it said.

But the Scottish Government was hopeful that the multi-year spending review announced by chancellor Rachel Reeves would help to provide greater funding certainty for the final years of the plan and beyond.

“We have struggled in previous years with only single-year budgets, making it very difficult to say whether a multi-year capital investment can go ahead,” it said.

It said it intended to publish a reset infrastructure pipeline to provide clarity on what would be delivered within the extended IIP period up to 2026/27.

Read More
Kerry Lorimer

Latest

The whole world is ready to boo Lane Kiffin. He’ll eventually get the last laugh – The New York Times

It has been less than a year since a documentary film, produced by ESPN and still streaming there, argued Lane Kiffin had matured. The film is called “The Many Lives of Lane Kiffin,” and it basically makes the argument that Kiffin, after two decades of relentlessly chaotic nomadism, of switching jobs, of heavy drinking, of

Davis Webb isn’t the only Bronco to blame for Week 1 debacle against the Chiefs

All the good vibes the Denver Broncos had built up over the offseason — the acquisition of Jaylen Waddle, Bo Nix's on-schedule return from the ankle surgery that cut his 2025 campaign short — wound up lasting less than two quarters of regular-season football. That's how long it took for the team's high-profile season opener

‘Make My Ears Bleed’ — NFL Fans Call Out Joe Buck’s Major Mistake During Chiefs-Broncos Monday Night Football Clash

It’s the first primetime game of the year for Joe Buck and Troy Aikman, and there’s been some rust to shake off. On a play in the second quarter, Troy Franklin took a jet sweep from Bo Nix, but Buck called Franklin by the wrong name. NFL fans were ready at their keyboards to troll

Newsletter

Don't miss

The whole world is ready to boo Lane Kiffin. He’ll eventually get the last laugh – The New York Times

It has been less than a year since a documentary film, produced by ESPN and still streaming there, argued Lane Kiffin had matured. The film is called “The Many Lives of Lane Kiffin,” and it basically makes the argument that Kiffin, after two decades of relentlessly chaotic nomadism, of switching jobs, of heavy drinking, of

Davis Webb isn’t the only Bronco to blame for Week 1 debacle against the Chiefs

All the good vibes the Denver Broncos had built up over the offseason — the acquisition of Jaylen Waddle, Bo Nix's on-schedule return from the ankle surgery that cut his 2025 campaign short — wound up lasting less than two quarters of regular-season football. That's how long it took for the team's high-profile season opener

‘Make My Ears Bleed’ — NFL Fans Call Out Joe Buck’s Major Mistake During Chiefs-Broncos Monday Night Football Clash

It’s the first primetime game of the year for Joe Buck and Troy Aikman, and there’s been some rust to shake off. On a play in the second quarter, Troy Franklin took a jet sweep from Bo Nix, but Buck called Franklin by the wrong name. NFL fans were ready at their keyboards to troll

Broncos vs. Chiefs live player stats, box score and match stats for Week 1 Monday Night Football

Patrick Mahomes and the Kansas City Chiefs are finally in action on Monday Night Football, kicking off the season and ending Week 1 as a whole with a showdown at Arrowhead Stadium against the bitter rival Denver Broncos. It should be a ton of fun as Mahomes makes his return after an ACL and LCL

‘Eye of the storm’: Business owner’s fight to keep nail tech siblings in country

A Whangārei beauty salon owner says her business may face trouble if she cannot find a way to keep her siblings in the country. Anna Vu owns AV Beauty Spa, and has worked in the city for 12 years. She said she had always struggled to find suitably skilled nail technicians and beauty staff and

What small business owners say they’d do differently, in hindsight

Working 60+ hours a week makes owners twelve times more likely to say their business is hurting their personal life. Australian small business owners are working through illness, skipping holidays and struggling to step away from their businesses, according to new research from insurer BizCover. The survey of 1,500 BizCover small business customers found more

Bright young business brains bring ideas to life

Friday 17 July, 2026 Young Cumbrian entrepreneurs showed off their innovative business ideas, from AI virtual assistants to African food, at two celebration events this week. Fifteen young people from Furness and West Cumbria aged 14 to 25 were selected to take part in the Positive Enterprise programme back in January...