Experts find 15% of Palace of Westminster spaces contain asbestos

Asbestos will be an important issue during the restoration of the Palace of Westminster after reports revealed 15 per cent of the building’s spaces are affected.

Experts also discovered more reinforced autoclaved aerated concrete (RAAC) – a historical building material that has exceeded its lifespan and which can pose structural safety risks – at the Grade I-listed complex.

At a Westminster committee meeting yesterday (19 March), representatives from the palace’s restoration and renewal teams updated MPs ahead of a debate on pushing ahead with the £3bn first phase of renovations.

Members of the Public Accounts Committee (PAC) were told that asbestos would be an issue after the latest reports showed 620 of the palace’s 3,999 spaces were identified as containing asbestos, mainly in the basement.

Spaces are distinct from rooms, and include many spaces behind walls, above ceilings, under floors, in stairwells, corridors, and service areas. The basement’s large footprint is divided into many smaller spaces for location mapping; these spaces are not conventional rooms.

The warning came ahead of procurement for the first phase of work, which is due to begin later this year, with a target to appoint many of the “strategic partners” in 2027.

Russ MacMillan, chief executive of the Palace of Westminster Restoration and Renewal Delivery Authority – the body responsible for designing, planning and managing the refurbishment of the Houses of Parliament – said his team would “not definitively know” the extent of the issue until they moved into each zone and took the fabric off the walls.

“We have done set sampling surveys and have estimated the quantity of asbestos on that basis: there are 90,000 square metres of coatings,” he said.

“Sometimes asbestos is best left but when we need to remove services it is often around them and the whole thing needs to be removed as an asbestos-contained material.”

In 2023, the PAC had estimated that asbestos was present in 2,500 areas of the parliamentary buildings and that its removal would require 300 people working for two-and-a-half years.

Charlotte Simmonds, managing director of the Restoration and Renewal Client Team – which oversees, instructs and holds to account the Delivery Authority – told yesterday’s committee hearing that more RAAC had also been found.

A 2023 report identified 16 areas of RAAC, predominantly in the upper committee corridor and T-block of the Houses of Parliament.

“In 2025, as the surveys continued, we found six additional areas in the north block and have mitigated it,” she said.

“There is an in-house project in place to rectify it but the main structural works will come through the restoration and renewal programme.”

Last month, parliament’s Restoration and Renewal Client Board – which is made up of members of the Commons and Lords, and is responsible for making critical strategic choices and recommendations relating to the restoration – announced that the first phase of work would hopefully begin this year.

Yesterday, the committee was told this phase would take seven years, with planning expected to be submitted in 2030.

However, MacMillan warned that if the planning process hit stumbling blocks, then each year of delay could cost up to £250m with inflationary costs.

Phase one of the scheme will include the construction of temporary chambers and office space, as well as a river jetty for material delivery and spoil removal.

PAC chair Sir Geoffrey Clifton-Brown raised concerns that the proposed costs and level of work were “not going to be delivered”, and called for a “clearly articulated vision”.

The start of work is conditional on approval from the House of Commons and House of Lords.

Simmonds said: “We need direction and decision to move forward.”

Last month’s report presented two options for the full refurbishment of the Houses of Parliament.

One was for a full temporary relocation of MPs and peers to enable works to take place over 19 to 24 years, at an inflation-adjusted cost of up to £15.6bn.

The other would see phased work dividing the palace into 14 zones, meaning no more than 30 per cent of the building would be out of use at any one time.

The report said this option would take 38 to 61 years and cost up to £39.2bn, including inflation.

MPs will be asked to debate and vote on the proposals. The client board has recommended that a final decision is taken no later than 2030.

Read More
Nicola Harley

Latest

I tested the Ninja AutoBarista Pro, and its smart Grind iQ feature demystifies grind settings so you don’t have to master coffee science for...

(Image credit: Karen Freeman / Future) Before I tested and reviewed the Ninja AutoBarista Pro, I had tried every kind of coffee brewing method over the years. I ground my own beans with a high-end 20-setting electric burr grinder. I researched how to get the ideal grind for each type of bean and brewing method.

Will Bitcoin Boom in 2026? Keeping Cryptocurrency Players Informed

By NFTevening March 6, 2026 Bitcoin has served to define the cryptocurrency community since its initial launch in 2009. While representing nothing more than an interesting investment opportunity at one time, this stablecoin has since become extremely popular throughout the online gaming community as an alternative payment method. However, even Bitcoin is not immune to

At climate summit, African leaders call for a bigger role in energy transition

African leaders called for regional cooperation and more climate investments, as the second Africa Climate Summit opened this Monday in Addis Ababa. Heads of state urged the continent to play a bigger role in the transition to a cleaner global economy. Speaking at the opening event, Ethiopian Prime Minister Abiy Ahmed said it's time to

USA Cruise, Morocco Take Control, Brazil Advance On World Cup Day 9

```html id="s7wthc" ``` By Newspot Nigeria Sports Desk Day Nine of the 2026 FIFA World Cup brought four more group-stage matches and a clear theme across the schedule: teams that needed control went out and took it. The United States defeated Australia 2-0 to book a place in the next round, Morocco edged Scotland to

Newsletter

Don't miss

I tested the Ninja AutoBarista Pro, and its smart Grind iQ feature demystifies grind settings so you don’t have to master coffee science for...

(Image credit: Karen Freeman / Future) Before I tested and reviewed the Ninja AutoBarista Pro, I had tried every kind of coffee brewing method over the years. I ground my own beans with a high-end 20-setting electric burr grinder. I researched how to get the ideal grind for each type of bean and brewing method.

Will Bitcoin Boom in 2026? Keeping Cryptocurrency Players Informed

By NFTevening March 6, 2026 Bitcoin has served to define the cryptocurrency community since its initial launch in 2009. While representing nothing more than an interesting investment opportunity at one time, this stablecoin has since become extremely popular throughout the online gaming community as an alternative payment method. However, even Bitcoin is not immune to

At climate summit, African leaders call for a bigger role in energy transition

African leaders called for regional cooperation and more climate investments, as the second Africa Climate Summit opened this Monday in Addis Ababa. Heads of state urged the continent to play a bigger role in the transition to a cleaner global economy. Speaking at the opening event, Ethiopian Prime Minister Abiy Ahmed said it's time to

USA Cruise, Morocco Take Control, Brazil Advance On World Cup Day 9

```html id="s7wthc" ``` By Newspot Nigeria Sports Desk Day Nine of the 2026 FIFA World Cup brought four more group-stage matches and a clear theme across the schedule: teams that needed control went out and took it. The United States defeated Australia 2-0 to book a place in the next round, Morocco edged Scotland to

Cancer: Nigeria empowers patients with N50m lifetime

….As 200 beneficiaries get N100.000 each  AKOR SYLVESTER, Abuja The federal government has unveiled a N50 million Social Determinants of Health (SDoH) Fund to support cancer patients to enable them to meet the challenges of transportation, accommodation, feeding and other non-medical issues. The Minister of State for Health and Social Welfare, Iziaq Adekunle Salako, who

Business seminar in Munich highlights Hong Kong’s strategic roles amidst global shifts (with photos)

Business seminar in Munich highlights Hong Kong's strategic roles amidst global shifts (with photos) ******************************************************************************************      The Hong Kong Economic and Trade Office, Berlin (HKETO Berlin), promoted Hong Kong's unique advantages and strategic roles at the seminar "Hong Kong's strategic role amidst geopolitical tensions" on June 18 (Munich time) in Munich, Germany.             Senior executives, investors

AI for business services: From job fears to productivity

AI for business services: From job fears to productivity

Business Insurance-AZ Achieves Record Response Times for 2026 Arizona Construction Bids

Business Insurance-AZ achieves milestone response speeds for commercial construction bids across Arizona, accelerating documentation delivery to keep local projects moving forward without delay. Phoenix, AZ, June 06-2026, ZEX PR WIRE — Business Insurance-AZ has achieved record-breaking processing speeds and response times for commercial construction bids throughout Arizona, directly supporting the state’s massive infrastructure and advanced manufacturing boom