London council to engage contractors earlier after ‘significant issues’

planning_strategy_shutterstock_2499289957.webp

A London council has changed its procurement methods and will make more of preconstruction services agreement (PCSA) methods after pausing the third phase of a housing programme due to financial pressures.

The Royal Borough of Kensington and Chelsea has delivered 168 homes under its £139.3m new homes programme, with another 94 still under construction.

But the first two phases of the work came in £3.9m over budget, a report reviewing its performance found.

It also noted that the council’s initial cost estimates were 40 per cent lower than they should have been because they did not include any contingencies or professional fees.

The report described “significant issues emerg[ing]” during delivery of the first phase of the schemes.

On its Acklam Road scheme, for 32 homes and two community spaces in Notting Hill, the report said the unspecified issues meant it was necessary to change contractors, with Willmott Dixon being replaced by Morgan Sindall.

The scheme ran from 2021-2024.

The report also said an 11-home scheme on the Silchester Estate in North Kensington was hit by “a prolonged and challenging contractual relationship” with contractor Buxton.

The construction contract – worth £6.4m according to data intelligence provider Glenigan – started in May 2022 and handover is due this month (February 2026).

The report also highlighted that the council removed consultant Perfect Circle as part of a move to address unsatisfactory performance.

The report said: “While there were contractor performance issues on Hewer Street, Kelso Cochrane and Silchester, the council’s initial client function was not as robust as it could have been, relying heavily on consultant employer’s agents.

“The initial employer’s agent was Perfect Circle and, in order to address unsatisfactory performance, a decision was made in late 2023 to replace Perfect Circle with PPP, and from then on client control and employer’s agent activity became aligned; and much stronger construction project management and tighter client control put the programme back on track for delivery.”

Willmott Dixon delivered the 20-home Hewer Street and 38-unit Kelso Cochrane elements of the programme.

The need to start construction across multiple sites by March 2022 in order to make use of a £33.6m Greater London Authority grant for affordable homes was cited as a reason why projects were started before their designs and costs were certain.

PCSAs are used to reduce future risk for the client.

A “structured procurement route decision tool” will now be used to take better account of “risk, market capacity, modern methods of construction, and price certainty”, the report said.

Future pre-award contract management plans will include defined KPIs, reporting requirements and remedies for supplier or contractor breach, “alongside enhanced supplier due diligence and ongoing performance management to ensure that contractual and delivery expectations are consistently met”.

The review also blamed construction inflation driven by issues such as the Covid  pandemic and the war in Ukraine for increased costs.

A third phase of the new homes programme, which the council announced in 2018, was due to deliver around 100 homes in total. Work was paused on two of its three sites due to cost concerns, with another scrapped altogether.

Some 157 of the 262 delivered during the first two phases are available for social rent.

Willmott Dixon, Morgan Sindall and Perfect Circle have been contacted for comment.

Read More
Ian Weinfass

Latest

3 Reasons to Apply for Inc.’s Power Partner Awards

Please enable JS and disable any ad blocker

World Cup betting markets shift after Jordan Henderson’s bizarre celebration injury

Jordan Henderson, the 36-year-old England midfielder, will miss the remainder of the 2026 FIFA World Cup after suffering a serious wrist and forearm injury during post-match celebrations on July 6. He wasn’t even playing when it happened. Henderson was an unused substitute in England’s dramatic 3-2 victory over Mexico in the round of 16. The

Kraken’s World Cup debut and Brazil’s collapse: what crypto gets from the beautiful game

Brazil came into the 2026 World Cup as one of the tournament favorites. They left in the Round of 16, beaten 2-1 by Norway, undone in part by a tactical decision that raised eyebrows across the footballing world: deploying 34-year-old Casemiro as a central striker, a position he hadn’t occupied in years. Haaland scored both

FIFA overturns Balogun’s red card, Trump intervenes for US World Cup match

https://www.nytimes.com/athletic/7424790/2026/07/06/folarin-balogun-red-belgium-explanation/ FIFA’s Disciplinary Committee has overturned the red card suspension of Folarin Balogun, a key player for the U.S. Men’s National Team, allowing him to participate in the upcoming Round of 16 match against Belgium. This decision, made under Article 27 of the FIFA Disciplinary Code, places Balogun on a one-year probationary period, enabling him

Newsletter

Don't miss

3 Reasons to Apply for Inc.’s Power Partner Awards

Please enable JS and disable any ad blocker

World Cup betting markets shift after Jordan Henderson’s bizarre celebration injury

Jordan Henderson, the 36-year-old England midfielder, will miss the remainder of the 2026 FIFA World Cup after suffering a serious wrist and forearm injury during post-match celebrations on July 6. He wasn’t even playing when it happened. Henderson was an unused substitute in England’s dramatic 3-2 victory over Mexico in the round of 16. The

Kraken’s World Cup debut and Brazil’s collapse: what crypto gets from the beautiful game

Brazil came into the 2026 World Cup as one of the tournament favorites. They left in the Round of 16, beaten 2-1 by Norway, undone in part by a tactical decision that raised eyebrows across the footballing world: deploying 34-year-old Casemiro as a central striker, a position he hadn’t occupied in years. Haaland scored both

FIFA overturns Balogun’s red card, Trump intervenes for US World Cup match

https://www.nytimes.com/athletic/7424790/2026/07/06/folarin-balogun-red-belgium-explanation/ FIFA’s Disciplinary Committee has overturned the red card suspension of Folarin Balogun, a key player for the U.S. Men’s National Team, allowing him to participate in the upcoming Round of 16 match against Belgium. This decision, made under Article 27 of the FIFA Disciplinary Code, places Balogun on a one-year probationary period, enabling him

UK Foreign Secretary Warns World Cannot Wait for ‘AI Hiroshima’ Before Acting

UK Foreign Secretary Yvette Cooper has warned that the world cannot wait for an AI equivalent of Hiroshima before acting, urging global powers to build consensus on artificial intelligence (AI) safety principles and standards. Cooper made the case in an essay, positioning Britain to lead international talks on the technology. ...

Business seminar in Munich highlights Hong Kong’s strategic roles amidst global shifts (with photos)

Business seminar in Munich highlights Hong Kong's strategic roles amidst global shifts (with photos) ******************************************************************************************      The Hong Kong Economic and Trade Office, Berlin (HKETO Berlin), promoted Hong Kong's unique advantages and strategic roles at the seminar "Hong Kong's strategic role amidst geopolitical tensions" on June 18 (Munich time) in Munich, Germany.             Senior executives, investors

AI for business services: From job fears to productivity

AI for business services: From job fears to productivity

Business Insurance-AZ Achieves Record Response Times for 2026 Arizona Construction Bids

Business Insurance-AZ achieves milestone response speeds for commercial construction bids across Arizona, accelerating documentation delivery to keep local projects moving forward without delay. Phoenix, AZ, June 06-2026, ZEX PR WIRE — Business Insurance-AZ has achieved record-breaking processing speeds and response times for commercial construction bids throughout Arizona, directly supporting the state’s massive infrastructure and advanced manufacturing boom