Two late payments no longer mean you can walk off site

Lawrence Pearce is a partner at law firm Holmes & Hills

The Supreme Court has brought clarity to a JCT termination issue that has been unsettling the construction industry since the Court of Appeal’s decision in Providence Building Services Ltd v Hexagon Housing Association Ltd last summer.

At stake was a deceptively simple question: can a contractor terminate a JCT Design and Build contract just because an employer has paid late more than once? The Court of Appeal said yes. The Supreme Court has now said no – and the difference matters.

“Curing a late payment within the contractual grace period really does wipe the slate clean”

The case arose out of a familiar scenario. Hexagon, the client, paid one interim payment late in December 2022. Providence, the contractor, served a formal “specified default” notice under clause 8.9.1 of the JCT Design and Build 2016 form. Hexagon then paid within the contract’s 28-day cure period.

Five months later, another payment was late, having been due by 17 May 2023 under a notice issued by Providence. This time the firm did not wait. It terminated the contract the next day, arguing that the second late payment was a “repetition” of the earlier default and that clause 8.9.4 entitled it to walk away.

The Court of Appeal agreed. It held that the contractor did not need to have acquired a prior right to terminate for the first late payment. Two late payments were enough.

That interpretation caused understandable concern in the market. Under that reading of JCT, an employer could cure a late payment exactly as the contract allows, yet still face termination months later if a further payment slipped – even by a day. The Supreme Court has now overturned that approach.

The judges focused on how clause 8.9 actually works. It sets up a two-stage mechanism. A late payment allows the contractor to serve a notice of default. If that default continues for 28 days, the contractor acquires a right to terminate under clause 8.9.3. That is the gateway. Only once that gateway has opened does the contract allow termination for a “repetition” of the same default under clause 8.9.4.

Hexagon’s December payment was late, but it was cured within the 28-day period. That meant Providence never acquired a termination right under clause 8.9.3. And because that gateway was never reached, the Supreme Court held that clause 8.9.4 could not be used later. Providence’s termination in May was therefore unlawful.

The court was also alive to the commercial consequences of the alternative interpretation. It described the Court of Appeal’s approach as a “sledgehammer to crack a nut”. On that logic, two payments a single day late could entitle a contractor to bring a major project to an abrupt end. That was not what the JCT wording, read properly, supported.

Restoring stability

For employers, developers and funders, the decision restores a measure of stability. It means that curing a late payment within the contractual grace period really does wipe the slate clean. A contractor cannot bank that default and deploy it later when relations deteriorate.

For contractors, the judgment is a reminder that termination is intended to be a response to serious, uncured payment failure – not a tactical option triggered by historic slippage. JCT still gives powerful tools for dealing with cashflow pressure, including interest, suspension and adjudication. But termination only comes into play once a default has been allowed to run on beyond the agreed cure period.

There is also a broader message here about standard forms. The Supreme Court was careful to say that courts should not bend JCT wording to address perceived industry unfairness. If the sector wants a tougher late-payment termination regime, that is a matter for the JCT drafting committee, not judicial interpretation.

The result is that the risk landscape has shifted back towards where many thought it sat before the Court of Appeal ruling in 2024. Repeated late payment is still serious. But under JCT Design and Build, it only becomes fatal if the first breach was bad enough to go uncured.

Two late payments no longer mean you can walk off site. Only one that was allowed to fester does.

Read More
Contributor

Latest

This company wants to stop underwater drones and even submarines with a whole new form of sonar technology

(Image credit: Ultra Maritime) Ultra Maritime pairs its Sea Spear passive sonar array with the AN/SSQ-125B active sonobuoy at the US Navy's Lanternfish 2026 exercise in a bid to detect underwater drones While neither sonar type is new, the distributed architecture that links both to Anduril's Seabed Sentry and the Navy's command systems generates usable

Windows NT 4.0 turns 30: when Microsoft brought the Windows 95 look to the enterprise

Serving tech enthusiasts for over 25 years. TechSpot means tech analysis and advice you can trust. GUI that made History: Windows NT 4.0 arrived in retail stores on August 24, 1996, marking a significant milestone in the history of PC operating systems. Microsoft developers backported the Windows 95 interface to the NT world, although they left quite

How to encourage smarter AI use in the classroom

This article is from Making AI Work , MIT Technology Review’s limited-run newsletter examining how to apply LLMs across industries. To receive it in your inbox, sign up here . Chatbots took many schools by surprise upon their release a few years ago. Suddenly, students carried an app in their phones that could magically answer

Predicting Kentucky’s ceiling and floor after the addition of Mark Mitchell

Basketball Kentucky basketball made the headlines this weekend as...

Newsletter

Don't miss

This company wants to stop underwater drones and even submarines with a whole new form of sonar technology

(Image credit: Ultra Maritime) Ultra Maritime pairs its Sea Spear passive sonar array with the AN/SSQ-125B active sonobuoy at the US Navy's Lanternfish 2026 exercise in a bid to detect underwater drones While neither sonar type is new, the distributed architecture that links both to Anduril's Seabed Sentry and the Navy's command systems generates usable

Windows NT 4.0 turns 30: when Microsoft brought the Windows 95 look to the enterprise

Serving tech enthusiasts for over 25 years. TechSpot means tech analysis and advice you can trust. GUI that made History: Windows NT 4.0 arrived in retail stores on August 24, 1996, marking a significant milestone in the history of PC operating systems. Microsoft developers backported the Windows 95 interface to the NT world, although they left quite

How to encourage smarter AI use in the classroom

This article is from Making AI Work , MIT Technology Review’s limited-run newsletter examining how to apply LLMs across industries. To receive it in your inbox, sign up here . Chatbots took many schools by surprise upon their release a few years ago. Suddenly, students carried an app in their phones that could magically answer

Predicting Kentucky’s ceiling and floor after the addition of Mark Mitchell

Basketball Kentucky basketball made the headlines this weekend as...

Sony Releases ‘Only on PS5’ Trailer

by William D'Angelo , posted 12 hours ago / 1,251 Views Sony Interactive Entertainment has released a new trailer titled "only on PS5" that features PlayStation 5 exclusive games. The games showcased includes Marvel's Wolverine, God of War Laufey, Ghost of Yotei, Saros, Gran Turismo 7, and Astro Bot. PlayStation had been for many years

Global Business Travel Spending to Hit Record $1.71 Trillion in 2026, While Trips Reach 1.84 Billion, Says GBTA Forecast

In Brief: GBTA’s latest Business Travel Index report shows spending gains driven by higher prices as geopolitical uncertainty and transportation pressures weigh on the outlook Global Business Travel Spending to Hit Record $1.71 Trillion in 2026, While Trips Reach 1.84 Billion, Says GBTA Forecast - Image Credit Unsplash+    Global business travel spending is forecast to

Boulevard Business Park: Saudi Arabia’s Bold Bet on Mixed-Use Development

Boulevard Business Park Saudi Arabia has marked another milestone in its urban and entertainment transformation with the completion of the Kingdom’s first entertainment-focused business park and corporate resort. This remarkable achievement reflects a new approach to commercial development that thoughtfully blends business, hospitality and leisure within a single destination. More Than an Office Park Located

How Chaoshan Business Was Built on Morals, Not Contracts

This is the second article in a series on China's southern Chaoshan region, exploring the history, culture, and identities behind its recent resurgence in the spotlight. Read Part 1. In the Chinatowns of early 20th-century Bangkok, Chinese laborers who had just collected their wages would make their way to the qiaopiju, a private institution that