Supreme Court rules against contractor in landmark late payment case

Supreme_Court_UK_shutterstock_2413574929.webp

Supreme Court

The Supreme Court has ruled that a contractor did not have the right under JCT design-and-build terms to terminate a contract after it was paid late twice.

The ruling ends a long-running dispute between Providence Building Services Ltd and client Hexagon Housing Association Ltd, which it was carrying out £7.2m of building work for in Purley, south London, from 2019 until 2022.

The Court of Appeal previously ruled in favour of the contractor’s decision to terminate its contract after Hexagon failed to pay an invoice on its scheduled date for the second time, even though Hexagon had paid within 28 days of receiving a first default notice.

In a new ruling on Thursday (15 January), Supreme Court judges unanimously found in favour of the client.

Lord Robert Reed said the natural meaning of clause 8.9.4 of the JCT (Joint Contracts Tribunal) Design and Build Contract (2016) was that the contractor needed to accrue a right to terminate the contract rather than being able to do so immediately. He said it refers back to a previous clause stressing the need for a default event to last 28 days.

He said that if a contractor was entitled to terminate a contract because it received two payments a single day late each, the contractual clause would be like using “a sledgehammer to crack a nut”.

“It would be less extreme if a second delay entitles the contractor to terminate the contract only where the first late payment has been delayed beyond the specified 28 days and has therefore been particularly serious,” he said.

The ruling also said it would be wrong to use the termination clause as a way of protecting contractors from cashflow difficulties, and dismissed the idea that clients and contractors have similar contractual obligations or termination rights.

Their respective termination clauses are written differently and “it is hard to see why that should be so if they were intended to have identical meanings”, Reed said.

During the building job, Hexagon failed to pay an invoice of £264,000 by its due date in November 2022.

Providence issued a formal notice of default, which warned Hexagon that it was in breach of its payment obligations. Hexagon made the payment within 28 days.

In April 2023, Hexagon failed to make another payment of £366,000 by its due date. After issuing a payment notice requiring payment on or before 17 May 2023, Providence terminated the contract on 18 May.

Hexagon paid the sum owed on 23 May and referred the dispute to an adjudicator, which found in its favour. The contractor then started legal action to make its case.

Mark London, senior partner at law firm Devonshires, which represented Hexagon in the case, had previously warned that the earlier judgment in favour of Providence had introduced “a significant risk to employers everywhere who, in the event of a specified default, will face the proverbial Sword of Damocles for the remainder of the contract”.

He said the ruling had created a “two strikes and you’re out” regime.

London said that he was “delighted” by the Supreme Court ruling, which “has brought certainty back to an industry where the use of the JCT standard form is common”.



Read analysis of yesterday’s Supreme Court judgment by Lawrence Pearce, a partner at law firm Holmes & Hills

Read More
Ian Weinfass

Latest

Everything you need to know about Greek yogurt and how it can meet your nutrition needs

Recipes Two-ingredient cheesecake. Turkish-style pasta. Baked yogurt toast. Bagels....

Cook This: 3 recipes from Istanbul, including one of Turkey’s favourite breakfasts

Recipes Özlem Warren shines a light on the culinary...

Green Sauce Tofu and More Recipes We Made This Week

Recipes It’s no secret that Bon Appétit editors cook...

Newsletter

Don't miss

Everything you need to know about Greek yogurt and how it can meet your nutrition needs

Recipes Two-ingredient cheesecake. Turkish-style pasta. Baked yogurt toast. Bagels....

Cook This: 3 recipes from Istanbul, including one of Turkey’s favourite breakfasts

Recipes Özlem Warren shines a light on the culinary...

Green Sauce Tofu and More Recipes We Made This Week

Recipes It’s no secret that Bon Appétit editors cook...

Marshmallow Creme vs. Fluff: The Sweet and Sticky Showdown

Recipes Skip to main content Taste of Home Taste of Home Do...

13 Real Business Trip Stories That Prove Work Travel Collects More Stories Than Miles

Real business trips almost never go the way the itinerary promised. They start with a confidently-packed suitcase and an eight-page agenda, and somewhere between the airport gate and the hotel breakfast they quietly turn into something nobody could have invented — equal parts comedy, chaos, and unscheduled adventure. These 13 real business trip moments are exactly that kind of work-trip plot

Your business texts could look like scam messages from July 1 if you don’t act now

From July 1, any branded SMS your business sends without a registered sender ID will be labelled “Unverified” and grouped with scam messages.  What’s happening: From 1 July 2026, any business or organisation that sends SMS using a branded name, such as “MyShop” or “AcmeServices”, instead of a phone number, must have that sender ID

Business groups are fighting Labor’s CGT changes. Here is where SMEs stand

Labor’s most contested tax reform in a generation cleared its first formal hurdle on Thursday and immediately ran into organised resistance. Treasurer Jim Chalmers introduced the government’s tax reform legislation to the House of Representatives on 28 May, bundling together four budget measures: the capital gains tax overhaul, new limits on negative gearing, a $250