Berkeley and Sisk in £4m dispute over east London bridge design flaws

sisk-32-1024x682.png

View of Sisk working around West Ham station

Berkeley Homes and John Sisk and Son are embroiled in a legal battle over who is responsible for design flaws that could cost more than £4m.

The dispute concerns a contract signed in December 2020 for Sisk to build three bridges and a new train station entrance at Twelve Trees Park, Berkeley’s 3,800-home scheme next to West Ham Station in east London.

Berekely Homes was the principal designer for the bridges during the pre-contract services agreement stage, employing architect HawkinsBrown and engineer Atkins.

However, Sisk submitted prices for the works under a pre-contract services agreement, signed in August 2018, and later took over as principal designer at the main contract stage, with the architect and engineer being novated.

Now Sisk says it has found “various errors in and/or omissions from the design” concerning piling works, steelwork, lifts, mechanical and electrical services, and consultant design works to bridges over the Docklands Light Railway and London Underground Jubilee Line.

It is unclear how many bridges are effected by the design errors. Court documents say “Sisk’s claims are not yet fully articulated”, adding that the design errors are not being contested as part of the court case.

Sisk says the design errors will directly lead to additional costs of about £2m, but that the total additional cost could be more than double this due to delays and disruption they will cause.

Sisk claims Berkeley is responsible for the consequences of the identified design problems. Berkeley argues that in signing the contract, Sisk “adopted the whole of the design and assumed full responsibility for its completeness and adequacy”.

Berkeley is seeking a number of declarations from the Technology and Construction Court, including confirmation of its view that Sisk took on responsibility for the project’s design “without qualification”.

It argues that Sisk should not be entitled to make any claim against it for breach of building contract resulting from errors or omissions in the design of the scheme. It is also making a claim for Sisk to cover its legal costs.

The legal action was launched in the Construction and Technology Court at the end of last month, with Berkeley setting out its claim in a document published last week. Sisk is yet to set out its full case.

Related articles

Read More
Jonathan Knott

Latest

SXSW 2026 Day 7 Photos: Highlights from Austin’s Music Festival

Music SXSW 2026 wrapped up with another incredible day...

Wizkid, Asake, Tems, and Burna Boy nominated for 2026 BET awards

MusicRead Later (0)Please login to bookmark Close The Nigerian music...

Newsletter

Don't miss

SXSW 2026 Day 7 Photos: Highlights from Austin’s Music Festival

Music SXSW 2026 wrapped up with another incredible day...

Wizkid, Asake, Tems, and Burna Boy nominated for 2026 BET awards

MusicRead Later (0)Please login to bookmark Close The Nigerian music...

Darius Rucker to receive Veterans Voice Award at AMAs

Music 1 of 5 | Darius Rucker, seen at...

Business seminar in Munich highlights Hong Kong’s strategic roles amidst global shifts (with photos)

Business seminar in Munich highlights Hong Kong's strategic roles amidst global shifts (with photos) ******************************************************************************************      The Hong Kong Economic and Trade Office, Berlin (HKETO Berlin), promoted Hong Kong's unique advantages and strategic roles at the seminar "Hong Kong's strategic role amidst geopolitical tensions" on June 18 (Munich time) in Munich, Germany.             Senior executives, investors

AI for business services: From job fears to productivity

AI for business services: From job fears to productivity

Business Insurance-AZ Achieves Record Response Times for 2026 Arizona Construction Bids

Business Insurance-AZ achieves milestone response speeds for commercial construction bids across Arizona, accelerating documentation delivery to keep local projects moving forward without delay. Phoenix, AZ, June 06-2026, ZEX PR WIRE — Business Insurance-AZ has achieved record-breaking processing speeds and response times for commercial construction bids throughout Arizona, directly supporting the state’s massive infrastructure and advanced manufacturing boom