How to deal with delay in construction contracts

Tim Seal is head of construction at Ridgemont

After long delays, it was recently announced that London Luton Airport had finally submitted revived plans for the construction of a second terminal. The story serves as a reminder that delay is a common feature of construction projects and should always be addressed in construction contracts so that there is a framework for dealing with it.

The Society of Construction Law’s Delay and Disruption Protocol provides useful guidance on some of the common delay and disruption issues that arise on construction projects (see the Introduction). As such, it is valuable reading for anyone who drafts and negotiates construction contracts.

The most common standard form of construction contract in the UK, ie, the JCT suite, deals with delay in the following way: the parties agree a start and a finish date, and the contractor provides a works programme for how it will achieve the latter. If the contractor becomes aware that completion of the works is likely to be delayed, it must notify the architect/contract administrator (ACA) and the ACA may then award an extension of time, thereby extending the completion date and/or award loss and expense to compensate for the delay. If the ACA won’t award an extension of time, the contractor will be liable for damages if it fails to meet the completion date.

Contract essentials

Using the JCT approach, here are some reminders about the key elements of delay that a contract should deal with:

  1. Realistic start and finish dates, plus a clear programme of works activities showing the sequence of works, and an obligation on the parties to keep that programme up to date as the project proceeds. This should create clarity and certainty as to expected timescales and hence reduce the risk of a dispute.
  2. Whether there will be sectional completion of the works or just one completion date.
  3. Notification of delay by the contractor, ie, set out the precise circumstances that trigger the notice requirement for the contractor, how quickly that notice must be served, what information as to delay it must contain and attach, and a requirement on the contractor to update that information should it subsequently change.
  4. The ACA’s response to the notice of delay in terms of accepting, partly accepting or rejecting the contractor’s application for more time. So, in particular, address the timetable for the response and what information and level of explanation it needs to contain so that the contractor can fully understand the thinking behind the decision.
  5. The grounds for an extension of time must also be clearly listed in the contract, ie, the circumstances in which the ACA is obliged to push the completion date back and relieve the contractor from a liability for damages. In the JCT, these are called ‘relevant events’. In the NEC, they are ‘compensation events’. Well-known examples of relevant events are variations, force majeure and adverse weather conditions. The extent to which COVID-19 was a relevant event attracted a great deal of commentary during the pandemic. Referring back to Luton Airport, deferment of the giving of possession of the site is a relevant event. These should all be things that are outside of the contractor’s control and hence for which it cannot be culpable.
  6. The other circumstances in which the ACA can adjust the completion date unilaterally, eg, if work is omitted from the contract, the ACA may seek to bring the completion date forward.
  7. The provision of practical completion or non-completion certificates by the ACA, to record the completion of the works or the fact that the contractual date has been missed.
  8. If the contractor misses the completion date and is not awarded an extension of time, then its liability in damages for delay should be dealt with in the contract; routinely in construction contracts, liability is agreed at contract stage by way of liquidated (ie, fixed) damages (LADs), so £x per week, for example. This prior agreement removes the need to then prove loss and achieves certainty around an acceptable level of liability. If, however, the level of LADs could be open to a subsequent accusation by the contractor that it is unreasonably high and hence unenforceable as a penalty, the calculation by which the LADs are agreed should be recorded and retained to demonstrate its rationale. A penalty is a punishment exerting undue pressure on a party to comply with the contract. The long-established test for a penalty has in recent years moved beyond simply whether or not it is a so-called ‘genuine pre-estimate of loss’.

If a contract deals with these things at least, it will go a long way to putting in place a workable structure for dealing with delay to the works.

Related articles

Read More
Contributor

Latest

Churchill Trends As Old Clip Of Tonto Dikeh Alleging She Funded Their Wedding Goes Viral

A video of Tonto Dikeh discussing her marriage to Olakunle Churchill has resurfaced online. The renewed interest follows Churchill’s recent comments about his current marriage to Rosy Meurer. In the video, Tonto shares her emotional experience during their wedding, claiming she financed most of the ceremony while pregnant. An old video of Nollywood actress Tonto

The Home Depot is blowing out Ryobi 40V electric yard tools during this limited spring sale

The system works flawlessly together so buying in makes chores simpler. Ryobi We may earn revenue from the products available on this page and participate in affiliate programs. Learn more › Sign Up For Goods 🛍️ Product news, reviews, and must-have deals. Spring lawn season is the right time to catch a Ryobi 40V outdoor

“I don’t think it’s a good idea”: Van Dijk breaks speaks out on Liverpool star’s exit rumours

Van Dijk breaks silence on key Liverpool teammate’s uncertain future April 29th 2026, 17:10 Alisson Becker hugs Virgil van Dijk (Photo by Carl Recine/Getty Images) Alisson Becker has been linked with a move away from the club at the end of the season. He has been an exceptional servant for Liverpool over the years, and

Watch: YG Teases New Boy Group; Reveals New Girl Group Member + Plans For BABYMONSTER And TREASURE

YG Entertainment has revealed some of its plans for the months ahead—along with the third member of its upcoming girl group! On April 30 at midnight KST, YG Entertainment released an announcement video in which founder Yang Hyun Suk spoke about what the agency has coming up. With BABYMONSTER gearing up to make a comeback

Newsletter

Don't miss

Churchill Trends As Old Clip Of Tonto Dikeh Alleging She Funded Their Wedding Goes Viral

A video of Tonto Dikeh discussing her marriage to Olakunle Churchill has resurfaced online. The renewed interest follows Churchill’s recent comments about his current marriage to Rosy Meurer. In the video, Tonto shares her emotional experience during their wedding, claiming she financed most of the ceremony while pregnant. An old video of Nollywood actress Tonto

The Home Depot is blowing out Ryobi 40V electric yard tools during this limited spring sale

The system works flawlessly together so buying in makes chores simpler. Ryobi We may earn revenue from the products available on this page and participate in affiliate programs. Learn more › Sign Up For Goods 🛍️ Product news, reviews, and must-have deals. Spring lawn season is the right time to catch a Ryobi 40V outdoor

“I don’t think it’s a good idea”: Van Dijk breaks speaks out on Liverpool star’s exit rumours

Van Dijk breaks silence on key Liverpool teammate’s uncertain future April 29th 2026, 17:10 Alisson Becker hugs Virgil van Dijk (Photo by Carl Recine/Getty Images) Alisson Becker has been linked with a move away from the club at the end of the season. He has been an exceptional servant for Liverpool over the years, and

Watch: YG Teases New Boy Group; Reveals New Girl Group Member + Plans For BABYMONSTER And TREASURE

YG Entertainment has revealed some of its plans for the months ahead—along with the third member of its upcoming girl group! On April 30 at midnight KST, YG Entertainment released an announcement video in which founder Yang Hyun Suk spoke about what the agency has coming up. With BABYMONSTER gearing up to make a comeback

We Investigated Pastor Jerry Eze For Alleged Money Laundering – EFCC Chairman

Ola Olukoyede, chairman of the Economic and Financial Crimes Commission (EFCC), has disclosed that Pastor Jerry Eze of Streams of Joy International was investigated for about six months over suspected money laundering before being cleared. The EFCC Chairman disclosed this on Wednesday while speaking at the Jerry Eze Foundation Business Grant Award Ceremony in Abuja.

Tesla’s Business Has Become Much More Diversified in Just the Past Five Years. Does That Make Its Stock a Better Buy Today?

Key Points Tesla's energy generation and storage segment generated 27% revenue growth last year. The company's non-automotive segments were able to help offset a double-digit decline in auto revenue in 2025. These 10 stocks could mint the next wave of millionaires › Tesla (NASDAQ: TSLA) is known for its electric vehicles (EVs), and while they

WD sees sustainability as key business driver in an ‘AI economy’

Hard drive company WD promoted long-term operations and sustainability executive Jackie Jung to become its first chief sustainability officer in February, as it steps up sales to companies building AI data centers. Her vision: Turn sustainability into a “brand” for WD, a strategy that reduces risk for the $6 billion company (formerly known as Western

5 Business Ideas Worth Starting in 2026

If there is one thing Nigerians understand well, it is how to spot opportunity inside hardship. In 2026, that mindset will matter more than ever. The economy is tough, competition is rising, and many people are looking for smarter ways to earn, build, and survive. But even in a difficult environment, some businesses still stand